County Officials Continue Search For Bouquet Canyon Road Solution

Los Angeles County Public Works officials are continuing the search for a solution to the dried-up wells and the flooded Bouquet Canyon Road by conducting research in the area and exploring the possibility of realigning the road.


Don’t miss a thing. Get breaking Santa Clarita news alerts delivered right to your inbox.


“The plan would be to have a road realignment, so the realignment would raise the road essentially out of the floodplain,” said Kerjon Lee, Los Angeles County Public Works public affairs manager. “In its current County Officials Continue Search For Bouquet Canyon Road Solutionconfiguration, water from the adjacent creek is allowed to reach the road. The plan is to realign the road.”

The plan could cost as much as $60 million and the county itself cannot pay for the realignment without other contributors, Lee said.

Related: LARC Ranch, Bouquet Canyon Community Still Out Of Water

“It’s not really a project yet per say, it’s something we’re discussing as a long term solution,” said Edel Viscarra, planning and public works deputy for Los Angeles County Supervisor Michael Antonovich. “This came out at the meetings we had with the state and Forest Service on long term versus short term solutions.”

County engineers have be conducting research in the Bouquet Canyon creek area, Viscarra said.

“Right now we’re working cooperatively with the other agencies and continue to work with the road issue,” Viscarra said. “Any major road project will take years to complete. The short term project is cleaning the creek. There are some studies that were performing right now and we are moving forward with that.”


Do you have a news tip? Call us at (661) 298-1220, or drop us a line at community@hometownstation.com.


Any impacts on wildlife or vegetation would have to be evaluated for the project, Lee said.

“Realignment would have some environmental impacts, we would have to have our plans reviewed and approved by the environmental regulatory agencies,” Lee said. “Forest Service would have to review the plans. We look to them for funding partners.”

Related: LARC Ranch Officials Raising Funds For Water Pipeline

Public Works officials are hoping to attain a Federal Lands Highway Access Program grant to help ease some of the financial burden for the realignment, Lee said. Officials expect the grant to open for proposals in October with a due date of January 2015.

“Anyone who is a stakeholder up there, we need to partner with them if and when [the realignment] is completed,” Viscarra said. “The main concern now is to find a short term solution to get water down to the residents of Bouquet.”

[node:title]KHTS AM 1220 - Santa Clarita News - Santa Clarita Radio


Article: [node:title]
Source: Santa Clarita News
Author: [node:author]


County Officials Continue Search For Bouquet Canyon Road Solution

Leave a Reply

Your email address will not be published. Required fields are marked *

*

This site uses Akismet to reduce spam. Learn how your comment data is processed.

About Jessica Boyer

Jessica is an award-winning journalist, photographer, videographer and artist. She has worked with news organizations including NBC Los Angeles, KHTS AM 1220, and the Pierce College Roundup News. She is studying to receive a Bachelor’s degree in Journalism with an emphasis on Photojournalism and a minor in Communications at California State University, Northridge. She has studied and worked in many fields including filmmaking, journalism, studio photography, and some graphic design. She began her journalism journey at the Arroyo Seco Conquestador News Network and the Saugus High School News Network.