Magic Mountain Road Improvements: May Update

Magic Mountain Parkway Widening: The construction of Magic Mountain Parkway widening (eastbound) is 70 percent complete. Curb and gutter, roadway paving, and traffic signal installation is in progress and tentatively scheduled to be complete in May 2009.

The Old Road Realignment: The construction is over 90 percent complete. The roadway will be fully capped and all driveways to restaurant row will be constructed by the end of the month. All businesses in the surrounding construction area will remain open during construction activities.


Northbound Off-Ramp: The contractor will begin the construction of the partial widening the beginning of the month. This work will not impact the existing detour for the northbound off-ramp. The complete ramp closure will take place at a later time with Caltrans’ approval. The ramp closure will remain for a maximum of four weeks.


Southbound On-Ramp: Opened on April 3, 2009.


Signage: Detours and roadway signs are in place to assist the operational needs of the public. Please proceed with caution. The City appreciates motorists’ continued patience and attention to the temporary roadway changes during this public improvement.

 

Check the City of Santa Clarita’s website at www.santa-clarita.com or the project hotline (661) 290-2297 for any extended major lane closures, detours, or additional news associated with this project.

Magic Mountain Road Improvements: May Update

Leave a Reply

Your email address will not be published. Required fields are marked *

*

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>

About hometown