The California Department of Transportation (Caltrans) plans to implement multiple freeway closures Sunday through Christmas Eve. 

In an effort to ease holiday traffic the closures will not take place Dec. 24 at 3 p.m. through Dec. 28.


Don’t miss a thing. Get breaking Santa Clarita news alerts delivered right to your inbox.


Referred to as the I-5 Truck Lane Project, Caltrans plans to implement the closures listed below as part of a project that is constructing truck lanes on I-5 between Pico Canyon Road/Lyons Avenue and the Antelope Valley Freeway (SR-14). 

Ramp closures will be nonconsecutive. Detours will be signed. No unusual levels of dust, noise or vibration are expected. Closures are subject to change.

For the safety of the construction crew and motorists, please be attentive to closures, slow for the cone zone, and move over one lane where possible.

Relates articles: Freeway Closures In The San Fernando Valley Postponed During Holidays

Closure information for this and other freeway projects is available on the Caltrans website

For real-time traffic information, visit quickmap.dot.ca.gov,go511.com, or call 5-1-1.

Closure Dates: Sunday, Dec. 22, through Tuesday, Dec. 24, 2013


Do you have a news tip? Call us at (661) 298-1220, or drop us a line at community@hometownstation.com.


NORTHBOUND I-5

Lanes 

  • Up to three lanes of northbound I-5 between the end of the existing truck lane and Lyons Ave. — 9 p.m. to 6 a.m. 

Note: At least one lane will be open at all times. The most restrictive closures (i.e., the most lanes closed) will occur between 1 a.m. and 4 a.m. 

SOUTHBOUND I-5 

Lanes 

  • Up to three lanes of southbound I-5 between Lyons Ave. and the end of the existing truck lane — 9 p.m. to 6 a.m. 

Note: At least one lane will be open at all times. The most restrictive closures (i.e., the most lanes closed) will occur between 1 a.m. and 4 a.m.

Connector 

  • Southbound I-5 to northbound SR-14 — 9 p.m. to 6 a.m.and 9 a.m. to 3 p.m. 

Off-Ramp 

  • Calgrove Blvd. — 9 p.m. to 6 a.m. and 9 a.m. to 3 p.m. 

About the Project 

This project is widening the freeway and bridges to add a truck lane to the outside of I-5 in both directions by paving the median area and outside shoulder, and shifting the mixed-flow lanes inward. Three median retaining walls and two short sections of outside retaining walls will be built to accommodate this widening. The southbound truck lane will extend from Pico Canyon Road/Lyons Avenue to SR-14 (3.7 miles), while the northbound lane will run from SR-14 to Gavin Canyon (1.4 miles).

The new truck lanes will ease traffic delays, improve goods movement, absorb traffic growth due to population increase (both residential and commercial), and enhance safety by separating truck traffic from passenger vehicles.

Construction began in May 2012 and will be completed in 2014.Funds administered by Metro. For more information, visit I-5info.com.

More information: traffic

[node:title]


Article: [node:title]
Source: Santa Clarita News
Author: [node:author]


Caltrans Announces I-5 Freeway Truck Lane Project Closures

Leave a Reply

Your email address will not be published. Required fields are marked *

*

This site uses Akismet to reduce spam. Learn how your comment data is processed.

About KHTS FM 98.1 & AM 1220

As Santa Clarita’s only local radio station, KHTS FM 98.1 & AM 1220 mixes in a combination of news, traffic, sports, along with your favorite adult contemporary hits by artists such as Rob Thomas, Taylor Swift, Katy Perry and Maroon 5. We are vibrant member of the Santa Clarita community. Our broadcast signal reaches all of the Santa Clarita Valley and parts of the high desert communities located in the Antelope Valley. We stream our talk shows over the web, reaching a potentially worldwide audience.