A Los Angeles judge has hit pause on a massive battery project planned for Acton, siding with local residents who argued the County bent the rules to get it approved.
The project, known as the Humidor Battery Energy Storage System (BESS), was pitched by Hecate Energy.
BESS would have covered about 12 acres of land in east Acton with 440 large battery cabinets, capable of storing enough electricity to power thousands of homes. A new high-voltage transmission line was also planned to connect the site to the grid.
But this week, Superior Court Judge Curtis Kin ruled the County’s approval of the project was improper, according to court documents. The judge said the site’s zoning, labeled “M-1” or Light Industrial, doesn’t actually allow for battery storage facilities.
“I’m very grateful to the community, because I think we all realize that we’ve dodged a bullet on this one,” said Ruthie Brock, the Director of Acton Takes Action, a community task force.
What went wrong
Because the zoning code doesn’t list battery storage as an official land use, County planners tried to treat the project as if it were an electric substation, which is allowed in M-1 zones. That interpretation let them approve the project quickly, without a full environmental study.
Judge Kin said that was a step too far. The zoning code only lets the County stretch the rules in heavier industrial zones, not in Acton’s lighter industrial zone. In short, the County didn’t have the authority to green-light the project where it wanted to put it.
What this means
The ruling wipes out the County’s approval and essentially stops the Humidor project in its tracks.
“It was truly a David and Goliath story,” said Brock. “The other big deal is there’s a BESS called the ‘Prairie Song Reliability Project’ that is going through the state process, not through LA County approval… they pointed to an interpretation memo, which our lawsuit has just taken the legs out from under… now they can’t rely upon that memo to help them with their approval.”
For now, Hecate Energy can’t move forward in Acton unless it finds another way to meet zoning requirements.
The judge didn’t weigh in on other arguments residents raised, like environmental concerns or consistency with Acton’s rural plan, because the zoning issue alone was enough to strike the project down.
Sponsored Articles
KHTS FM 98.1 and AM 1220 is Santa Clarita’s only local radio station. KHTS mixes in a combination of news, traffic, sports, and features along with your favorite adult contemporary hits. Santa Clarita news and features are delivered throughout the day over our airwaves, on our website and through a variety of social media platforms. Our KHTS national award-winning daily news briefs are now read daily by 34,000+ residents. A vibrant member of the Santa Clarita community, the KHTS broadcast signal reaches all of the Santa Clarita Valley and parts of the high desert communities located in the Antelope Valley. The station streams its talk shows over the web, reaching a potentially worldwide audience. Follow @KHTSRadio on Facebook, Twitter, and Instagram.